Jiangsu revs up major investment project construction

2022-03-10 11:30:16 | 来源:ourjiangsu.com

字号变大| 字号变小


East China’s Jiangsu province has
stepped up the construction of major investment projects and ensured their smooth progress through every possible effort so as to fulfill goals for social and economic development. JSBC has the story.

On March 8, concrete-pouring on the first T beam of the second bid section of the Yangkou-Lvsigang Railway was finished, marking the start of full-scale construction of the railway with a total investment of about 9.9 billion yuan and a total length of about 85 kilometers.

When official production starts, the construction party will meet the task of prefabricating 4 pieces per day and storing 350 pieces of T beams.

Wang Fujie, Project Manager of the Second Bid Section of Yangkou-Lvsigang Railway, China Railway 19th Bureau Group Co., Ltd.

Our initial scale is designed

to produce 4 beams per day

and we will expand

at the end of the year

By then

we can produce 10 beams per day

and store 100 beams

to ensure that the railway

will open to traffic by the end of 2023

The Yangkou-Lvsigang Railway will connect the coastal port areas including Yangkou, Tongzhou Bay, Dongzao and Lvsi.

Jiangsu is speeding up the construction of the South Yangtze River Intercity Railway, and the construction of 3 km of the 4 km ballast-less track base plate in the first 4 bid sections has been completed.

Duan Pengcheng, South Yangtze River Intercity Railway Project Department, China Railway Guangzhou Bureau

We plan to complete the laying

of track slabs on August 30, 2022

The construction party is speeding up the construction of the station building of Jintan Station of the South Yangtze Intercity Railway. In the Jiangyin section, ballastless track construction is underway.

Wang Kaichen, Project Manager of the South Yangtze Intercity Railway Project

It is expected

that in the first half of this year

the construction of the ballastless track slab

of the Beijing-Shanghai Expressway Bridge

will be completed

laying the foundation for the next track laying

The construction party has relocated the communication, electricity, water supply and drainage and gas pipelines of the Jiangyin section of the South Yangtze River Intercity Railway.

The builders have completed the construction of the basic structure of the Jiangyin High-speed Railway Comprehensive Passenger Terminal Station, and the construction of the track-bearing layer and the first-floor column is in progress. The laying of the long rails is expected to start in August to ensure the opening to traffic by the end of the year.

layer